| Date: | Area: | Streets/Bays Affected: | Time: | Customers Affected: | Reference: | Reason: | Note: |
|---|---|---|---|---|---|---|---|
| Tuesday 16th December | Anakiwa | Thompson Place, Anakiwa Road, Lady Cobham Grove, Beauchamp Lane | 8:30am-6:00pm | 95 | 4978 | Pole Replacement | Cancelled |
| Tuesday 16th December | Renwick | Blicks Road | 8:30am-1:00pm | 16 | 5225 | Crossarm Replacement | Cancelled |
| Tuesday 16th December | Port Underwood | Tumbledown Bay Road | 8:30am-6:00pm | 33 | 5250 | Pole Replacement | Cancelled |
| Tuesday 16th December | Blenheim | High Street | 6:00am-8:00am | 1 | 5337 | DP Box Replacement | |
| Wednesday 17th December | French Pass | Deep Bay | 8:00am-6:00pm | 2 | 5124 | HV Line Alterations | |
| Wednesday 17th December | Mahakipawa | Queen Charlotte Drive | 8:30am-6:00pm | 21 | 5321 | Maintenance | |
| Wednesday 17th December | Tuamarina | Pembers Road, Neal Road, Pukaka Road | 8:00am-5:00pm | 6 | 5369 | Pole Installation | |
| Thursday 18th December | Renwick | Alma Street | 11:00am-4:00pm | 1 | 5216 | Pole Replacement | |
| Thursday 18th December | Spring Creek | Hathaway Street, Peninsula Road, Ferry Road, Gouland Road, Dodson Street | 8:30am-6:00pm | 53 | 5238 | Asset Relocation | |
| Thursday 18th December | Pelorus | Maungatapu Road | 8:30am-6:00pm | 27 | 5258 | Pole Replacement | |
| Thursday 18th December | Blenheim | High Street | 5:00am-8:00am | 1 | 5337 | DP Box Replacement | |
| Friday 19th December | French Pass | Deep Bay | 8:00am-1:00pm | 2 | 5126 | HV Line Alterations |